Hiranandani Hospital, Powai, Mumbai
2,58,334 sq ft
Hospital
Energy Savings
Hiranandani Hospital partnered with 75F to save 3,37,576 kWh of energy

Challenge:

Hiranandani Hospital was seeking future-ready energy saving solutions to reduce its energy consumption and bring down operating costs. Several of its HVAC assets were dated and unable to operate at optimum levels. Equipped with only a partially working building management solution, the facility could not access real-time monitoring and establish control of its AHUs or Chillers. The client’s facility management team needed automation and centralized monitoring of key operational areas with simplified energy management dashboards and reports. Tata Power Trading Company Limited (TPTCL) – an integrated power company that supplies electricity to Hiranandani Hospital and a 75F partner, recognized these needs. Upgradation via 75F’s IoT-based BMS was essential for the facility to apply for green building certification.

Solution:

The 75F team conducted an on-site survey resulting in a clear pathway to deliver 75F’s proprietary IoT-based BMS solutions to help Hiranandani Hospital achieve its energy efficiency goals. A key challenge was that Hiranandani Hospital was a critical-care environment that could not shut down HVAC systems due to the sensitive nature of its operations. The 75F team implemented the necessary solutions utilizing the most appropriate configurations allowing the client facility team access to customized dashboards displaying key data on energy consumption, emissions, and spend. 75F’s solutions serve many areas of the facility including the reception, lobby, outpatient department, laboratories, and patient rooms.

Installation and Execution:

75F’s specialized execution team worked nights to ensure there were no shutdowns across HVAC systems allowing for smooth implementation. After a detailed assessment of the client’s requirements and critical infrastructure systems, our team implemented several custom tailored solutions.

Result:

Energy Savings:

75F's IoT-based Building Management System (BMS) facilitated significant energy savings for Hiranandani Hospital. Within 12 months of installation from May 2023 to May 2024 the client has saved a total of 3,37,576 kWh across the hospital's Chiller Plant and Air Handling Unit (AHU) operations.

Fast and Easy Installation

Installation at the facility was supported by the deep knowledge and expertise of the 75F team. Work commenced in mid-January with installation activities completed by mid-April of 2023, totaling just 90 days for retrofitting the entire hospital, with zero downtime. 

Energy Management Dashboard

To give complete visibility on all key performance energy parameters, the 75F team delivered customized dashboards to provide clarity across key performance metrics to Hiranandani Hospital’s facility management team. 

Managed Services

75F's Managed Services Team took care of the site post-commissioning and made sure that the site operated at peak energy-efficiency levels.